[112-114] Tank Leak Test Setup Screen 1

Legend for numbered boxes
The Tank Leak Test Setup allows you to establish and enter
the method, timing, and duration of automatic leak tests. You
must have a Mag 1 or 2 probe installed to perform leak tests.
If you are using the In-Tank Leak Test feature for underground
storage tank regulatory compliance, be sure the leak test
limits you establish and enter comply with the test type,
accuracy, and frequency requirements as defined by local,
county, state, federal and any other regulatory authority
governing your site.
In addition, set the test time for a period when no fueling from
or bulk delivery to the tank will occur. Such activity during a
leak test procedure will result in inaccurate leak test results.
1
Test Rate [112] - You can set the leak test rate at 0.2 gph
(0.76 lph) (default) or 0.1 gph (0.38 lph). Selecting 0.1
gph (0.38 lph) requires a Mag 1 probe. Touch the Down
Arrow button to the right of the window and enter the
desired choice.
2
Early Stop [113] - Disabled is the default setting. When
enabled this feature will prevent an In-Tank Leak Test from
starting under the following conditions:
• Tank volume is less than Leak Min Periodic vlaue or
Leak Min Annual value.
• It is less than 8 hours from a delivery.
• The product temperature is less than 0°F (-17.6°C) or
more than +100°F (+37.4°C).
• There is too little fuel in tank.
Touch the Down Arrow button to the right of the window
and enter the desired choice.
01-01-2000
ALL FUNCTIONS NORMAL
12:00 AM
1
[112]
2
EARLY STOP
[113]
3
[114]
1
2
[112-114] Tank Leak Test Setup Screen 1
4
SAME ALL TANKS
TANK 1
0.2 GPH
3
4
5
3
Test Duration [114] - The maximum duration is 24 hours.
There is a minimum duration of two hours for 0.2 gph
(0.76 lph) tests and three hours for 0.1 gph (0.38 lph)
tests.
Note: If you have Early Stop enabled and the console
determines that an Tank Leak Test has passed the test is
completed before the duration times out. Default
duration is 2 hours. Touch the Down Arrow button to the
right of the window and enter the desired choice.
4
Same All Tanks button - Touch this button to transfer
identical selections made on this screen for Tank 1 to All
Tanks (opens the confirm Same All Tanks Screen on
page 59).
The Tank Leak Test setup concludes on page 60.