Furuno ECDIS FMD-3100 Installation Manual page 16

Electronic chart display and information system
Hide thumbs Also See for ECDIS FMD-3100:
Table of Contents

Advertisement

1. MOUNTING
For OP24-62
To install the optional keyboard (Type: SKB-E3U, contained in OP24-62), do the fol-
lowing procedure.
1. Referring to the following steps, fit the static electricity prevention sheet (included
as optional kit) to the keyboard, then fix the keyboard at the installation location
using the double-sided tape (Tape V/H, supplied with the optional kit).
1) Remove the protective film from one side of the supplied double-sided tape,
then stick the tape to the 4 edges of the rear of the keyboard.
2) Remove the protective film on both sides of the
sheet, then fit the sheet to the keyboard.
Note: The sheet is extremely thin and should be
handled with care.
3) Remove the protective film from the double-sid-
ed tape on the rear of the keyboard, then fix the
sheet to the tape.
2. Stick the smaller velcro tape (Fastener, 5 pcs., sup-
plied with the optional kit) to the four corners of the
rear of the keyboard and to the EMI core.
3. Fit the larger velcro tape (Fastener, 5 pcs., supplied
with the optional kit) to the smaller tape.
4. Remove the protective film from the larger velcro tape.
5. Fit the keyboard at the installation location.
6. Depending on the installation location and environment, move and then fit the EMI
cores as required.
The following points should be observed when moving the EMI cores:
• Do not remove or disconnect the USB cable.
• Do not apply undue stress or weight to the base of the cable connection on the
keyboard.
• The EMI core must not be suspended freely as this puts strain on the cable.
• Re-wrap the cable around the EMI core a total of 6 times. The cable should
pass through the EMI core a total of 7 times.
If you change the position, re-wrap cable
1-8
EMI core
around the core 6 times.
Protective film
Sheet

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents