Starting; Figure 11 Electrical Connection Electronic Controller 70304G - M&C SP Series Instruction Manual

Hide thumbs Also See for SP Series:
Table of Contents

Advertisement

Caution
Figure 11
Electrical connection electronic controller 70304G
16

STARTING

 Before starting up check whether the mains power supply voltage corresponds with the information stated on
the probe's nameplate.
 If there is a built-in ball valve you should also check, if it is closed. In case of hand-operated ball valves, the control
grip must be located at the right-hand stop.
 Switch on mains power supply.
 Check the rated value setting on the built-in thermostat or on the external controller.
 The total heating-up time is approximately 2 hours. After about 1 hour the probe is already sufficiently heated
for the temperature to have exceeded the temperature failure alarm value (30 °C below rated value), but it still
takes about another hour until operating temperature is reached.
28
If not all cable glands are used for the electrical connection of the temperature regulator,
the remaining ones must be shut in order to guarantee the tightness of the housing.