Procedure for Functional Check
of Replacement Components _________
Microprocessor Controller (Computer) Board
Phase 7 Coin Models
Upon completing installation of the replacement
microprocessor controller (computer) board, reestablish
power to the dryer.
Start the drying cycle by pressing any temperature selection
key (HI, MED, or LO).
Verify that the applicable indicator lights on the
microprocessor controller (computer) board are lit. (Refer to
the illustration below.)
113237 - 15
Phase 7 Non-Coin Models
Upon completing installation of the replacement
microprocessor controller (computer) board, reestablish
power to the dryer.
Start the drying cycle by pressing any of the preset cycles in
letters A-F.
Verify that the applicable indicator lights on the
microprocessor controller (computer) board are lit. (Refer to
the illustration below.)
www.adclaundry.com
25

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the AD-25V and is the answer not in the manual?

Questions and answers

Table of Contents