Installation; Mechanical Installation; Side-By-Side Installation - Trane TR150 Quick Manual

Hide thumbs Also See for TR150:
Table of Contents

Advertisement

Installation

3 Installation

3.1 Mechanical Installation

3.1.1 Side-by-side Installation

3
3
The frequency converter can be mounted side by side but requires the clearance above and below for cooling.
Size
IP class
TR150
H1
H2
H3
H4
H5
H6
H7
H8
H9
H10
TR170
H2
H9
Table 3.1 Clearance Required for Cooling
NOTICE
With IP21/NEMA Type1 option kit mounted, a distance of 50 mm (2 in) between the units is required.
6
3x200–240 V
IP20
0.25–1.5 (0.33–2)
IP20
2.2 (3)
IP20
3.7 (5)
IP20
5.5–7.5 (7.5–10)
IP20
11 (15)
IP20
15–18.5 (20–25)
IP20
22–30 (30–40)
IP20
37–45 (50–60)
IP20
IP20
IP20
1.5 (2)
IP20
Power [kW (hp)]
3x380–480 V
0.37–1.5 (0.5–2)
2.2–4 (3–5)
5.5–7.5 (7.5–10)
11–15 (15–20)
18.5–22 (25–30)
30–45 (40–60)
18.5–30 (25–40)
55–75 (70–100)
90 (125)
75–90 (100–125)
1.5(2)
08/2020 All rights reserved.
Clearance above/below [mm (in)]
3x525–600 V
37–55 (50–70)
2.2–7.5 (3–10)
11–15 (15–20)
1.5 (2)
100 (4)
100 (4)
100 (4)
100 (4)
100 (4)
200 (7.9)
200 (7.9)
225 (8.9)
100 (4)
200 (7.9)
100 (4)
100 (4)
BAS-SVX58D-EN