Notes: (continued)
•
•
•
•
•
•
7705 SAR-F Installation Guide
To provide necessary stability, ensure that the equipment rack is bolted to the floor. Ceiling
brackets are useful to provide additional stability.
The equipment rack must be properly grounded.
Install the chassis in the equipment rack before installing SFPs.
Maintain a clearance of at least 2.5 in. (6.4 cm) at the front of the router for cable
management.
Maintain a clearance of at least 3 in. (7.6 cm) on each side of the router to ensure adequate
air intake and exhaust. When mounting the router in a rack, ensure that the rack complies
with all requirements outlined in
The 7705 SAR-F includes factory-installed, rack-mounting brackets to mount the router in
a 19-inch equipment rack.
Chassis Location Requirements on page 52
Site Preparation
.
Page 49