8.3

Pre-Commissioning Process

Perform the necessary steps to complete the pre-commissioning process:
1. The customer must review the LV-NKN-CS-0006 pre-Commissioning Checklist and prepare
the VFD for the commissioning procedure.
2. Ensure the Pre-Commissioning checklist procedure is complete prior to arrival of Qualified
Siemens Personnel for commissioning of the VFD.
Note
The VFD must be commissioned by Qualified Siemens Personnel only.
Type 6SR5 Air-Cooled
Operating Instructions, AK, A5E39390112
Commissioning
8.3 Pre-Commissioning Process
53