3.3.4
Installation of the probe with cut-in fitting up to 100 bar
1) Refer to ordering guide
Fig. 18
EE360 probe up to 100 bar
The sensing probe must be mounted horizontally or vertically, pointing downwards. When possible, a
drip sheet should be fitted for each mounting.
Mounting the clamping ring screw connection
Safety instructions for pressure-tight screw connection:
• The system must not be vented by releasing the union nuts.
• Do not assemble and tighten pipe screw connections if the system is under pressure.
• Always use the correct thread sealant on conical pipe threads.
• Never rotate the screw connection body. Instead, hold the screw connection body securely and turn
the union nut.
• Avoid unnecessary disassembly of unused pipe screw connections.
Installation instructions:
• Tighten the union nuts finger-tight.
• Mark the union nuts at the 6 o' clock position.
• Hold the screw connection body tight and tighten the union nuts with 1 ¼ turns to
the 9 'o clock position.
Fig. 19
Clamping ring installation
Assembly with high pressure applications and applications with a high security factor:
• Tighten the union nuts until the pipe can no longer be turned by hand or can no longer be moved
axially in the fitting.
• Mark the union nuts at the 6 o' clock position.
• Hold the screw connection body tight and tighten the union nuts with 1 ¼ turns to
the 9 'o clock position.
Re-mounting:
• Slide measurement sensor with clamping rings into the fitting as far as it will go.
• Tighten the nut "fingertight", then tighten by approx. a ¼ turn using a spanner.
22
code "cable length"
code "probe length"
1)
1/2" ISO, 1/2" NPT or
1/2" weld
(1450 psi)
1)
Operating instructions for EE360 Moisture in Oil Transmitter

Advertisement

Table of Contents
loading

Table of Contents