baltur TBG 45 PN-V Manual User Instructions page 49

Two stage gas burner with inverter
Hide thumbs Also See for TBG 45 PN-V:
Table of Contents

Advertisement

Available languages

Available languages

PREPARATION FOR CONNECTION
WITH TRAIN TURNED UPWARDS
If you wish to turn the train entrance upwards, before applying the
burner to the boiler, follow the subsequent procedure.
1) Following the instructions detailed in the "Maintenance"
paragraph, extract the mixer assembly and remove the screw
(1) which connect the unit's forward movement rod (2) to the
gas delivery pipe (3).
(3) Remove the screw (5) which connects the gas mixer (6) to the
pipe (figure 1).
2) Turn the bend coupling through 180° (4) and the mixer (6), in
such a way that the inlet gas is turned upwards (figure 1). Again
fix the mixer and the unit's forward movement rod to the gas
delivery pipe.
3) Now remove the 4 nuts (7) in figure 2, disassemble the flame
pipe (8) from the relative stud bolts, reposition them with the
threaded connection for fixing the gas train upwards.
4) To complete the operation fix the flame pipe to the scroll burner
and finally reposition the mixing unit in the relative housing.
At this point it is possible to install the burner in the boiler with the
valve train as shown in configuration 9 illustrated in paragraph "Gas
train assembly".
21 / 26
0006081483_201512
fig. 1
fig-2