BURNER CONNECTION TO THE BOILER
ASSEMBLING THE HEAD UNIT
• Adjust the connection flange -19 position loosening the screws -6.
The burner head must penetrate to the extent requested by the
generator manufacturer.
• Position insulating seal -13 on the sleeve, placing rope -2 between
the flange and the seal.
• Anchor the flange of the head unit -14 to the boiler -19 with the stud
bolts, washers and nuts provided -7.
DANGER / CAUTION
Completely seal the gap between the burner sleeve and
the hole in the refractory material inside the boiler door with
suitable material.
ASSEMBLING THE GAS TRAIN
The gas train can be assembled in different ways: -8 and (8a).
DANGER / CAUTION
In case of very large valves, e.g. DN65 or DN80, make sure
there is a suitable support to prevent excessive stress on the
gas train fitting.
ASSEMBLY OF VENTILATION SYSTEM
Position the half-hinge on the burner scroll in line with those on the
combustion head assembly.
• Insert the hinge pin -10 in the position considered most suitable
• Connect the cables (switch on and ionisation) to the corresponding
electrodes, close the hinge, locking the burner by means of screws
-11.
• Insert the gas throttle control lever on the shaft and block it with
the specific nut.
12 / 34