Hardware Start-Up - Honeywell ENCAL 3000 Hardware Manual

Gas chromatograph
Table of Contents

Advertisement

7.2

Hardware Start-up

Mount the cap on the unit, hand-tight fixed. The marked screws in the following figure
are security screws. Screw out the security screws to prevent removing of the cap by
accident or ignorance.
Figure 7.1: Location of security screws to fix the cap after mounting on the base
Complete all the commissioning work in the specified sequence to avoid possible
damage and fault situations affecting the device.
Steps Hardware Start- - - - up
Steps Hardware Start
Steps Hardware Start
Steps Hardware Start
up
up / / / / Commissioning
up
1.
Open the carrier gas cylinder (setting: 0.55 MPag).
2.
Open the process calibration gas cylinder (setting: 0.4 MPag)
3.
Open the process gas (recommended setting 0.2 MPag )
4.
Switch on the power supply.
5.
Connect with RGC 3000 (future steps in software manual)
The unit will automatically start-up (as defined in the software). The start-up sequence
takes about 5 minutes, including temperature and pressure stabilisation, and system
flushing. After this sequence the unit is ready for the software configuration.If you wish
to make any changes, please refer to software manual or contact your TAC.
The device can be fitted with an optional additional heating system for use in
temperatures below freezing. Further details of this option is listet in the annex.
EnCal 3000 Hardware Manual
Commissioning
Commissioning
Commissioning
!Obey the explosion protection regulations!
!Obey the explosion protection regulations!
!Obey the explosion protection regulations!
!Obey the explosion protection regulations!
73022344 o
COMMISSIONING AND DECOMMISSIONING
82