Figure 3-16 Securing the antiseismic kits to the cabinet
Step 3 Reinstall the rear panel.
Step 4 Adjust the cabinet position so that the expansion bolt holes are aligned with the eight holes at
the bottom of the cabinet.
Step 5 Secure the two antiseismic kits at the front and rear of the cabinet to the floor using eight M12
expansion bolts, as shown in
Figure 3-17 Securing the antiseismic kits to the floor
----End
Issue 01 (2020-04-27)
Figure
3-17.
Copyright © Huawei Technologies Co., Ltd.
3 Installation
59