JRR200 Route Reflector Hardware Guide
JRR200 Site Guidelines and Requirements
JRR200 Route Reflector Environmental Specifications
30
Table 14: Site Preparation Checklist for JRR200 Route Reflector (continued)
Item or Task
Rack or Cabinet
Verify that your rack or cabinet meets the
minimum requirements for the installation
of the device.
Plan rack location, including required space
clearances.
Secure the rack or cabinet to the floor and
building structure.
Cables
Acquire cables and connectors:
Determine the number of cables needed
based on your planned configuration.
Review the maximum distance allowed
for each cable. Choose the length of
cable based on the distance between
the hardware components being
connected.
Plan the cable routing and management.
JRR200 Route Reflector Environmental Specifications on page 30
General Site Guidelines on page 31
Site Electrical Wiring Guidelines on page 31
Clearance Requirements for JRR200 Route Reflector Airflow and Hardware
Maintenance on page 32
Table 15 on page 30
provides the required environmental conditions for normal JRR200
Route Reflector operations. In addition, the site must be as dust-free as possible because
dust can clog air intake vents, reducing the efficiency of the cooling system.
Table 15: Environmental Specifications
Description
Value
Altitude
No performance degradation up to 6,562 feet (2000 meters).
Additional
Performed
Information
By
"JRR200 Rack and
Cabinet
Requirements" on
page 34
Copyright © 2018, Juniper Networks, Inc.
Date
Notes