Tools And Equipment Required For The Installation; Equipment Required For Post-Upgrade Adjustments - Keysight Technologies E8364-60108 Installation Note

Microwave network analyzers
Table of Contents

Advertisement

General Information
Installation Procedure for the Upgrade Kit
Step 3. Raise the Receiver Deck.
Step 4. Remove the Existing Cables.
Step 5. Install the Attenuators and Bias Tees.
Step 6. Install the Option UNL Cables.
Step 7. Lower and Fasten the Receiver Deck and Connect the Bias Tee Control Cables.
Step 8. Replace the Lower Front Panel Overlay (Option 014 Only).
Step 9. Reinstall the Front Panel Assembly and Front Panel Jumpers (Option 014 Only).
Step 10. Reinstall the Outer Cover.
Step 11. Enable Option UNL.
Step 12. Perform Post-Upgrade Adjustments and Calibration.

Tools and Equipment Required for the Installation

Description
T-8 TORX driver (set to 5 in-lbs)
T-10 TORX driver (set to 9 in-lbs)
T-20 TORX driver (set to 21 in-lbs)
5/16-inch torque wrench (set to 10 in-lbs)
5/16-inch torque wrench (set to 21 in-lbs) (Option 014 only)
ESD grounding wrist strap
5-ft grounding cord for wrist strap
2 x 4 ft conductive table mat and 15-ft grounding wire
ESD heel strap (for use with conductive floors)
Use a 5/16-inch torque wrench set to 10 in-lbs on all cable connections
except the front-panel connectors to which the front-panel jumpers attach
(Option 014). Use a 5/16-inch torque wrench set to 21 in-lbs for these
connections.

Equipment Required for Post-Upgrade Adjustments

Equipment Type
Power meter
Power sensor, 2.4 mm
Adapter, 2.4 mm (f) to 2.4 mm (f)
RF cable, 2.4 mm (f) to 2.4 mm (f)
6
Qty
1
1
1
1
1
1
1
1
1
Model or
Part Number
E4418B/E4419B
8487A
11900B
85133C
Keysight E8363B/C and E8364B/C Installation Note
Part Number
N/A
N/A
N/A
N/A
N/A
9300-1367
9300-0980
9300-0797
9300-1308
Al ternate Model or Part
Number
E4418A/E4419A
None
85056-60007
85133E

Advertisement