WD-Z2 Series Installation Guidelines Rev.5
③ Radio reception with the receiver installed in a corner of the area [× Not good]
The relay load tends to be biased toward some of the transmitters, so the wireless path is not
distributed well.
(2-1-2) Receiver Height
It is recommended to install the transmitter for all equipment at a height where there is minimal
obstruction, and the receiver should be installed at about the same height as the transmitter.
Important
When selecting the receiver installation location, give sufficient consideration and refer to "(3) Stable
wireless communication Zone".
Also, it is recommended to temporarily install the receiver at a location where the "Radio Wave
Environment Investigation Service" is provided, establish a test period for about one week, and proceed
with a final installation if there are no issues.