Verifying The Communication - ABB Relion 670 Series Installation And Commissioning Manual

Generator protection
Hide thumbs Also See for Relion 670 Series:
Table of Contents

Advertisement

Section 14
Establishing connection and verifying the IEC 61850 communication
14.3
146
Set Operation to On and GOOSE to the port used (for example
OEM311_AB).
2.
Enable redundant IEC 61850-8-1 communication for port AB and CD
2.1. Enable redundant communication.
Navigate to: Main menu/Settings/general settings/Communication/
Ethernet configuration/Rear OEM - redundant PRP
Set values for Operation, IPAddress and IPMask. Operation must be set
to On.
The IED will restart after confirmation. Menu items Rear OEM - port
AB and Rear OEM - port CD are hidden in local HMI after restart but
are visible in PST where the values for parameter Mode is set to Duo.

Verifying the communication

Connect your PC to the nearby switch and ping the connected IED and the
Substation Master PC, to verify that the communication is working (up to the
transport layer).
The best way to verify the communication up to the application layer is to use a
protocol analyzer, for example, an Ethereal that is connected to the substation bus,
and monitor the communication."
Verifying redundant IEC 61850-8-1 communication
Ensure that the IED receives IEC 61850-8-1 data on both port AB and CD. Browse
in the local HMI to Main menu/Diagnostics/Communication/Redundant PRP
and check that both signals LAN-A-STATUS and LAN-B-STATUS are shown as
Ok. Remove the optical connection to one of the ports AB or CD. Verify that either
signal LAN-A-STATUS or LAN-B-STATUS (depending on which connection that
was removed) are shown as Error and the that other signal is shown as Ok. Be sure
to re-connect the removed connection after completed verification.
1MRK 502 029-UEN A
Installation and commissioning manual