8
Guide for the Installation
Basic Steps
NOTE
Please refer to the planning documents for the installation.
Please also refer to the technical data (see chapter "Technical Data" on page 20).
The wall tube must be installed at the sampling point before the probe is installed
(see chapter "Preparing for Installation" on page 9).
Step
Action
1
Unpack the supplied parts (see section "Unpacking and Delivery
Form" on page 12).
2
Install the gas sampling probe (see section "Assembling Probe 2" on
page 13).
3
Carry out the electrical connection (see sections
"Requirements and Procedures for Electrical Connection" on page 16
and "Electrical Connections for Probe 2" on page 17).
After you have carried out these steps, probe 2 is operative.
Need help?
Do you have a question about the Gas Sampling Probe 2 and is the answer not in the manual?
Questions and answers