4. CONSTRUCTION

During the environmental survey all installation not only ATU and SPU, but also places for DPU,
cables, protective pipes, should be carefully considered.
4.1.

Requirement for Radar Stand

1)
The radar stand is used when installing the weather radar at a specific observation point.
2)
The antenna unit is mounted on the top of the radar stand, and the Signal Processing Unit is
usually mounted on the bottom part of radar stand.
3)
The installed location of the radar must have proper load bearing resistance and durability to
support a radar stand.
4)
The radar stand must be considered not to fall down in strong wind or earthquake.
5)
Keep strictly checking the safe distance when deciding the height of the radar stand written in
the "Operator's manual".
6)
ATU where work is often done at high places, a scaffold that service engineer can work at
high places, ladders that must reach to ATU, sites where safety belts for fall prevention, etc.
can be fixed must be required.
The radar stand should be installed in the level within ±2 degrees.
7)
ATU should be installed in the level within ±0.2 degrees. Refer to the item "Leveling the
8)
antenna unit" in section 5.
SPU should be installed in the level within ±2 degrees.
9)
Leveling ±2°
ATU
Leveling ±2°
(Radar stand)
Figure 4.1: Leveling of radar stand
Leveling ±2°
Figure 4.2: Leveling of SPU base
17
Leveling ±0.2°
(Radar)
Radar stand