2. PROCEDURE
This section explains the procedures for installing the PBX system. The installer should follow the flowchart proce-
dure shown in
Figure
3-2. In the flowchart, an NAP (NEC Action Procedure) Number, denoted on the right side of
each action, refers to the details for each procedure.
CHAPTER 3
Page 24
Revision 2.0
START
UNPACKING
MARKING AND DRILLING
INSTALLATION OF
MAIN EQUIPMENT
PWR CA-A AND
BUS CABLE CONNECTION
CONNECTION OF
BATTERY
CABLE RUNNING
TO MDF
TERMINATION OF
CABLES ON MDF
SWITCH SETTING OF
CIRCUIT CARDS
A
Figure 3-2 Procedure Flowchart
NDA-24219
NAP- 200-001
NAP- 200-002
NAP- 200-003
NAP- 200-004
NAP- 200-005
NAP- 200-006
NAP- 200-007
NAP- 200-008