Servicing The Pto Shaft Cross And Bearing - Toro Groundmaster Series Service Manual

Table of Contents

Advertisement

Servicing the PTO Shaft Cross and Bearing

Chassis: Service and Repairs
g221216
1.
End yoke
2.
Cross and bearing kit
3.
Snap ring (4 each)
1. Remove the PTO shaft from the machine; refer to
the PTO Shaft (page
2. Remove the snap rings that secure the bearings in the yokes.
Support the yokes when removing and installing the bearings to
prevent damage.
3. Use a press to remove the cross and bearings from the yokes. Clean the
PTO shaft yokes.
4. Install new cross and bearings as follows:
A. Apply a thick layer of grease to the bearing bores in the end yoke and
shaft yoke.
B. Press 1 bearing partially into the yoke.
C. Insert the cross into the yoke and bearing.
D. Hold the cross in alignment and press the bearing in until it hits the yoke.
E. Install the snap ring into the yoke groove to secure installed bearing.
F. Place second bearing into the yoke bore and onto the cross shaft. Press
the bearing into the yoke and secure with the snap ring.
G. Repeat the procedure for the other yoke.
H. Apply grease to the cross until it comes out of all the 4 bearing cups.
5. Ensure that the assembled joint moves without any binding. Lightly rap the
yoke lugs with a soft-faced hammer to remove slight binding. If binding
continues, disassemble the joint to identify the source of binding.
6. Install the PTO shaft to the machine; refer to
PTO Shaft (page
7–19).
Figure 121
4.
Shaft yoke
5.
Grease fitting
7–19).
IMPORTANT
Page 7–20
Removing and Installing
Removing and Installing the
Groundsmaster
®
3200, 3300 and 3310
19240SL Rev A

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents