Special Set-Up Procedure
WARNING – Turn off electrical power
and disconnect power cord from
electrical supply before beginning special
set-up procedure, if power cord is not
disconnected, severe injury to personnel
could result.

Changing Tape Leg Length

(From 50 to 70 mm [2 to 2-3/4 In])
Notes
1. Changing tape leg lengths to 70 mm
[2.75 in] increases minimum box height
to 120 mm [4.75 in].
2. When changing tape leg length, both
upper and lower taping heads must be
adjusted to apply the same tape leg
lengths.
UPPER TAPING HEAD
Upper taping head is built into case sealer frame,
however, it has the same mechanical components
as the lower head which is a separate assembly.
To convert the upper head to 70 mm [2.75 in] tape
leg length, refer to Section II, "Adjustments –
Changing Tape Leg Lengths", page 13.
LOWER TAPING HEAD
Remove the lower taping head from the case sealer
by lifting the head straight up out of the machine
bed.
WARNING – Use care when working
near blades as blades are extremely
sharp. If care is not taken, severe injury
to personnel could result.
Converting the lower head to apply 70 mm [2.75 in]
tape legs is the same as the upper head. Refer to
Section II, "Adjustments – Changing Tape Leg
Lengths", page 13.
(Continued)

Box Height Range

(Outer Column – Re-Positioning)
Moving the outer columns to the upper set of
mounting holes increases the maximum box size
(height) handled by the 800asb case sealer from
570 mm [22.38 in] to 670 mm [26.38 in]. Note – this
also increases the minimum box height from 70
mm [2.75 in] to 108 mm [4.25 in].
To Re-position the outer columns:
1. Disconnect emergency stop switch enclosure
2. Disconnect emergency stop electrical conduit
3. Remove special nut from the bottom of each
4. Remove plastic column cap from the top of each
5. Crank upper assembly up, out of plastic nuts.
28
WARNING – It is recommended that
no less than two people assist on this
set-up or severe injury or equipment
damage could result.
from front/top of upper assembly.
mounting bracket from upper assembly.
column lead screw. Figure 5-3A.
outer column as shown in Figure 5-3B.
Lift upper assembly up and out of outer
columns. Be careful not to damage lead screws.
Figure 5-3C.
WARNING – Upper assembly weight
is approximately 35 kg [75 lbs]. Lift
with hoist or be sure to have adequate
help available to physically lift upper
assembly up and out of outer columns.

Advertisement

Table of Contents
loading

This manual is also suitable for:

29600

Table of Contents