Life Safety - HP Performance Optimized Datacenter 20c Maintenance And Service Manual

Table of Contents

Advertisement

Component to be inspected

Life safety

Component to be inspected
Manual EPO shunt trip
Thermal EPO shunt trip
EPO System Test
Emergency Lighting
Exit signs
Emergency egress
Task
Inspect the door operation and
inspect the door gaskets for water
and air leaks.
Visually inspect the paint. Perform
prep and touch-up as necessary.
Task
EPO FUNCTIONAL TEST
Manually initiate EPO with the
internal and external push buttons
(if installed) in succession. (Verify
all shunt-trips on all panels trip.)
EPO FUNCTIONAL TEST
Initiate a thermal (automatic) EPO
shutdown via the EPO
temperature switches located in
the hot aisle. (Verify all shunt-trips
on all panels trip.)
EPO NON-FUNCTIONAL TEST
Mode Key Switch Test - rotate
keyed switch through all modes.
ARMED MODE - Verify:
Power Indicator - White
Armed Light - White
BYPASS MODE - Verify
Bypass Light - Green
TEST MODE - Verify:
Test Light - Amber
Press EPO button (each in
succession) and thermal trip to
verify:
Reset Light - White
Audible alarm
Visual lamp indicator
Replace light upon failure
Verify emergency lighting is
visible when all lighting is off and
the POD doors are shut.
Visually inspect Tritium exit signs
for operation or damage.
Replace as necessary.
Personnel door emergency egress
panic bars. (Visual and
operational inspection.)
Frequency
Capable Party
Annually
Qualified personnel
Annually
Qualified personnel
Frequency
Capable Party
Annually
Qualified personnel
Annually
Qualified personnel
Annually
Qualified personnel
Every 2 years
Qualified personnel
Every 2 years
Qualified personnel
Bi-annually
Qualified personnel
Periodic maintenance 75

Advertisement

Table of Contents
loading

Table of Contents