Installing Cables Between The Sun2000-150Ktl-S0 And The Isolation Transformer - Huawei PowerCube 5000 Installation Manual

Hide thumbs Also See for PowerCube 5000:
Table of Contents

Advertisement

PowerCube 5000 (SUN2000-150KTL-S0)
Installation Guide
Figure 7-11 Installing the parallel EPO control cable
----End
7.4 Installing Cables Between the SUN2000-150KTL-S0
and the Isolation Transformer
Procedure
Step 1 Install surge protection, high-temperature, and overtemperature alarm signal cables between
the SUN2000-150KTL-S0 and the isolation transformer.
Issue 03 (2020-04-10)
After startup, press the emergency stop buttons in cabinets 1 and 2. The two cabinets should stop.
Copyright © Huawei Technologies Co., Ltd.
7 Installing Cables
55

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sun2000-150ktl-s0

Table of Contents