Figure 7-11 Installing the parallel EPO control cable
----End
7.4 Installing Cables Between the SUN2000-150KTL-S0
and the Isolation Transformer
Procedure
Step 1 Install surge protection, high-temperature, and overtemperature alarm signal cables between
the SUN2000-150KTL-S0 and the isolation transformer.
Issue 03 (2020-04-10)
After startup, press the emergency stop buttons in cabinets 1 and 2. The two cabinets should stop.