Step 1 Set all the switches to the appropriate status based on site requirements.
Step 2 Observe the power system for 1 hour and check that no alarm is displayed on the liquid
crystal display (LCD) of the monitoring module and that the voltage and current for batteries
and loads are normal.
Step 3 Reinstall the removed panel if any.
Step 4 Check whether the paint on the surface of the cabinet is intact. Repair any damaged paint.
Step 5 Lock the cabinet door and hand over the key to the administrator.
Step 6 Ensure that the site is clean before you leave the site.