Subsequent Operations - Huawei PowerCube 5000 Installation Manual

Hide thumbs Also See for PowerCube 5000:
Table of Contents

Advertisement

PowerCube 5000 (SUN2000-150KTL-S0)
Installation Guide
Procedure
Step 1 Set all the switches to the appropriate status based on site requirements.
Step 2 Observe the power system for 1 hour and check that no alarm is displayed on the liquid
crystal display (LCD) of the monitoring module and that the voltage and current for batteries
and loads are normal.
Step 3 Reinstall the removed panel if any.
Step 4 Check whether the paint on the surface of the cabinet is intact. Repair any damaged paint.
Step 5 Lock the cabinet door and hand over the key to the administrator.
Step 6 Ensure that the site is clean before you leave the site.
----End
Issue 03 (2020-04-10)
10

Subsequent Operations

Copyright © Huawei Technologies Co., Ltd.
10 Subsequent Operations
87

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sun2000-150ktl-s0

Table of Contents