Prerequisites
If two SUN2000-150KTL-S0 cabinets are deployed, perform the following steps to install
cables.
Procedure
Step 1 Install communications cables between ECMs.
Figure 7-6 Installing communications cables between ECMs
Step 2 Install a communications cable between ECC500Ss.