Shutting Down And Powering Off A Parallel System - Huawei PowerCube 5000 Installation Manual

Hide thumbs Also See for PowerCube 5000:
Table of Contents

Advertisement

PowerCube 5000 (SUN2000-150KTL-S0)
Installation Guide
Procedure
Step 1 Tap the start/stop button on the MDU main menu, or shut down the system on the WebUI to
disconnect the system output.
Step 2 Turn off the AC output switch, battery string switch, and isolation transformer disconnector.
Step 3 Turn off the solar input switch and AC input switch.
Step 4 The loads power off completely. The control panel and indicators turn off.
----End

9.7.2 Shutting Down and Powering Off a Parallel System

Prerequisites
Ensure that the output load is transferred or there is no major load so that system power-off is
allowed. Once the integrated equipment is shut down, there is no power output from the
output end.
Procedure
Step 1 Tap the start/stop button in the MDU main menu of a cabinet or shut down the system on the
WebUI to disconnect the system output.
Step 2 Turn off all AC output switches, battery string switches, and isolation transformer
disconnectors.
Step 3 Turn off the solar input switch and AC input switch.
Step 4 The loads power off completely. The control panel and indicators turn off.
----End
Issue 03 (2020-04-10)
Copyright © Huawei Technologies Co., Ltd.
9 Power-on and Commissioning
86

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sun2000-150ktl-s0

Table of Contents