Step 2 Cover a PVC corrugated pipe over the cable parts outside the cabinet and secure the PVC
corrugated pipe to the cable hole.
----End
7.7 Installing Battery Input Power Cables
Procedure
Step 1 Switch all external battery circuit breakers to OFF.
Step 2 Prepare power cables.
1.
2.
Step 3 Install the negative battery string cable at the BAT- screw in the cabinet.
Step 4 Install the positive battery string cable at the BAT+ screw in the cabinet.
Figure 7-19 Installing battery input power cables
(1) Battery switch box
Issue 03 (2020-04-10)
Prepare suitable-length cables based on site requirements.