Following are the steps needed to install the Tire Changer. Perform them in the order shown.
1. Review the installation Safety Rules.
2. Make sure you have the necessary Tools.
3. Find an appropriate Location.
4. Make sure there is adequate Clearance around and above.
5. Unpack the Tire Changer.
6. Install the Storage Cabinet.
7. Install the Bead Breaker Mechanism.
8. Anchor the Tire Changer.
9. Connect to Power.
10. Connect to pressurized Air.
11. Prepare the Lube Bucket.
12. Grease the Assist Tower Posts.
13. Test the Tire Changer.
14. Review the Final Checklist.