Omc; Install Equipment On Outdoor Structure; Attach Enb To Support Pole (If Needed); Figure 3-16: Active Status (Omc) - Baicells Nova-233 G2 Installation Installation

Outdoor 2x1w tdd enodeb
Hide thumbs Also See for Nova-233 G2:
Table of Contents

Advertisement

3.6.2 OMC

To check the eNB's status using the OMC, follow the steps below.
1. Open a Web browser, and enter the CloudCore address:
https://cloudcore.cloudapp.net/cloudcore/
2. Go to eNB > Monitor, and check the Active Status column as shown in Figure 3–16. If
the status is not reported as active, contact Baicells support.
Figure 3–16: Active Status (OMC)

3.7 Install Equipment on Outdoor Structure

Installing the eNB should be performed only by qualified installation technicians per the
operator's network design plan and according to industry standard safety precautions.
Hoisting the RF antenna and eNB onto a tower or other structure may require 2 to 4 people.
Follow standard safety precautions for working at the expected height and as required for
electrical installations. Always wear proper tower climbing safety gear and follow tower
climbing safety certification rules.
This section provides guidance for pole installations and positioning the equipment on a tower,
roof, or other structure, as well as outside wall installations.
NOTE: It does not matter if the eNB or the antenna is installed first, or together at
the same time.

3.7.1 Attach eNB to Support Pole (if Needed)

Follow the steps below to attach the eNB to a support pole. The pole diameter must be
between 1.6 to 3.9 inches (40 to 100 millimeters). The suggested height of the eNB on the pole
is at least 47 inches (120 cm).
NOTE: Some newer eNB models ship with a slightly different bracket, but the
installation steps are generally the same. Both types are illustrated below.
1.
The mounting bracket comes preassembled from the manufacturer. Take off the outer
omega clamps, as shown in Figure 3-17.