Finalising Work - DeDietrich EVODENS PRO Amc 45 Service Manual

Control panel & high-efficiency wall-hung gas boiler
Table of Contents

Advertisement

8 Maintenance
Fig.147
Re-assemble and place the flue gas
pipe
13
12
8.5

Finalising work

44
AMC Pro
10. Place the upper part of the flue gas pipe into the lower part up to the
11. Place the flue gas pipe with the line between the two arrows facing
12. Place the return sensor connector.
13. Place the flue gas temperature sensor (if connected).
10
10
11
11
AD-4000133-01
1. Fit all removed parts in the reverse order.
2. Fill the siphon with water.
3. Put the siphon back in place.
4. Carefully open the water tap.
5. Fill the central heating system with water.
6. Vent the central heating system.
7. Top up with more water if necessary.
8. Check the tightness of the gas and water connections.
9. Put the boiler back into operation.
10. Carry out an auto-detect when a control board has been replaced or
mark.
forward into the condensate collector up to the mark.
Caution
During inspection and maintenance operations, always replace all
gaskets on the parts removed.
removed from the boiler.
7725106 - v.01 - 05062019