Installing the Front Cover
Step 2
Secure the cable guides with the four M4x6mm screws supplied with the cable guide kit. The recommended
maximum torque is 10 in-lb (1.12 N-m)
Installing the Front Cover
Before you begin
The front cover protects the system from dust. Ensure the disturbance to cable routing is minimal to avoid
loss of connection.
Procedure
Step 1
Place the cable sleeve close to the router.
Step 2
Secure the fiber or cable bundle in the cable tube. Slide the cable tube into the cable sleeve as shown in the
following figure.
Step 3
Slide the front cover over the cable tube and secure it with the fasteners on the cable cover.
Figure 15: Installing the Front Cover Assembly
1
3
Watch
Cisco ASR 920-10SZ-PD and Cisco ASR-920-8S4Z-PD Aggregation Services Router Hardware Installation Guide
36
Cable Sleeve
Front Cover
Protecting the Cisco ASR 920-10SZ-PD Router
Installing the Cisco ASR 920-10SZ-PD and Cisco ASR-920-8S4Z-PD Routers
2
Cable Tube
—
—
(Video).