SolarEdge SE5000H-AU Installation Manual page 80

Ev charging single phase inverter with setapp configuration
Table of Contents

Advertisement

79
  Energy Meter DIP Switches
To connect the Energy Meter to the inverter:
 1. Connect one end of the communication cable to the Energy Meter, as explained in
the Energy Meter's installation guide.
 2. Remove the seal from one of the openings inthe communication gland at the
bottom of the inverter and insert the RS485 wires from the meter through the
opening.
 3. Remove the 3-pin connector from the RS485-1 port on the communication board.
 4. Loosen the screws of the connector and remove the DC-to-DC unit wires. Twist the
DC-to-DC unit wires together with the Energy Meter wires (B with B, A with A, G
with G).
Figure 30: ID and termination DIP switches
Figure 31: Meter connection
EV Charging Single Phase Inverter MAN-01-00629-1.2