Verifying The Connection - SolarEdge SE5000H-AU Installation Manual

Ev charging single phase inverter with setapp configuration
Table of Contents

Advertisement

63
  Verifying the Connection

Verifying the Connection

After connecting and configuring a communication option, perform the following
steps to check that the connection to the monitoring server has been successfully
established.
 1. Access the Status screen:
 a. If not already ON - turn ON AC to the inverter by turning ON the circuit breaker
on the main distribution panel.
 b. Open SetApp and follow the instructions on the screen (scan the inverter bar-
code; move the ON/OFF/P switch to P position (for less than 5 sec) and release).
The mobile device creates a Wi-Fi connection with the inverter and displays the
main Commissioning screen.
Power
Optimisers
Connected
Status
Production
CosPhi
1.00
Voltage
Commissioning
 2. Check that S_OK - Server Connected status appears in the main inverter section.
 3. Scroll down to the Communication section and check that the communication
options are as required. For more information refer to Communication Status on
page 46.
Status
Inverter
SN 07318000C
Voltage
Frequency
S_OK
Server Connected
Switch
ON
Limit
Country
No Limit
Netherlands
Temp
Fan
EV Charging Single Phase Inverter MAN-01-00629-1.2

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents