6.1.2 Commissioning

Context
Perform system commissioning and power-on strictly according to the system manual and
ATS instructions. For any changes in operations and parameters, consult Huawei engineers.
Otherwise, system commissioning or power-on may fail, or even the cabinet is damaged.
Procedure
Step 1 Turn on the circuit breakers of the ATS operation mechanism (Q1 and Q2 in the left lower
part at the rear of the cabinet) to power on the ATS operation mechanism.
Step 2 Check whether the controller has alarms. If an alarm exists, rectify the fault first.
Step 3 Press the locking latch on the ATS panel, pull out the handle, and insert it into the slot.
Step 4 Check the ATS Motor/Manual selection lever, and flip it to the Motor mode.
Step 5 Check the AC input and configuration status of the ATS.
After the AC input is normal, the ATS controller starts. Check and set ATS parameters based
on the AC input parameters.
Issue 04 (2018-04-20)
Item
Positive and negative battery terminals are
connected correctly. Check this item by viewing
the color or label of the battery input cable.
The AC input voltage is within the rated input
range.
The battery input voltage is within the rated range.
On the default screen, hold down
main menu screen, select system configuration and press
A password is required to log in to the configurations page. Set the password by using the Up, Down,
and Enter buttons. The initial password is 0001.
The following table lists the system configuration attributes and values.
Copyright © Huawei Technologies Co., Ltd.
Result
□ Yes
No
□ Yes
No
□ Yes
No
. The main menu screen is displayed. On the
6 Operations
Remar
ks
.
156