Gas supply
Gas pipe sizing must consider the gas input to this appliance, as well as other gas
appliances in the premises. The gas supply termination is inside the heater, and
enters from the lower right hand side of the appliance.
approx. 320 mm
Electrical supply
The Ember is fitted with a 1.5 m power cord and 3-pin plug.
The power cord passes through a slot in the back left hand
corner of the appliance.
The connection is either direct wired* or connected to a
power point within the cavity. This must be connected to
a dedicated earthed power point. The electric isolation
switch must be accessible after the appliance has been
installed.
The fire must not be located immediately below a socket
outlet (potential fire hazard).
If the supply cord is damaged, it must be replaced by a licensed tradesperson. This must be a
genuine replacement part available from Rinnai.
* Consult a qualified electrician if direct wiring is required as it must comply with AS/NZS 5601 and AS/NZS 3000 and other
relevant local regulations
8 | Ember Installation Guide: 12890-B 02-18
Purging the gas supply
Foreign materials and debris such as swarf,
filings etc. must be purged from the gas
supply. Failure to do so may cause damage to
the control valve causing it to malfunction.
Gas connection
A small spanner has been provided, located
in the commissioning pouch on top of the
PCB cover, to help with the gas connection as
space is quite tight. Please return the spanner
to the pouch when finished.
The use of a rubber hose for any gas
connection to a fixed appliance is not
authorised by the manufacturer.

Enclosure dimensions

The Ember must be positioned within the enclosure on a flat level surface that
allows free movement of the appliance. The enclosure must be capable of
supporting 1.5 times the weight of the Ember.
Masonry
Actual chimney size needs to be at least 200 x 200 mm
for the two flexi flues to fit down the chimney.
600
700
W-width
600 mm
700 mm
Infill panel*
600-750 mm
700-850 mm
Masonry frame*
N/A
700-785 mm
H-height
600 mm
600 mm
Infill panel*
600-675 mm
600-675 mm
Masonry frame*
N/A
600-638 mm
D-depth
400 mm min. 400 mm min.
* Enclosure dimensions can be larger if using an infill
panel or a masonry frame.
Corner installations
Ember 600
Mock chimney
600
700
W-width
700 mm
800 mm
H-height
700 mm
700 mm
D-depth
400 mm min. 400 mm min.
Framing dimensions above are before the zero clearance
frame is fitted.
For mock chimney installations the Ember MUST BE
installed with the Ember Zero Clearance frame, which
gives the required clearances to combustibles.
Ember 700