Making The Wall Penetration For The Interconnecting Piping - Carrier P5 Series Owners And Installation Manual

Split system air conditioner
Table of Contents

Advertisement

INDOOR UNIT INSTALLATION

2) Making the Wall Penetration for the Interconnecting Piping

Rear Piping
• It is best for the piping to go through the wall behind the unit. So that the unit hides the pipes.
• For this method of installation, make a 65mm diameter hole in the wall at either point L or R. ( Figure. 5 )
Indoor side
Side or Bottom Piping
• Remove the knock-out in the unit and pass the pipes through the wall.
• The pipe should slope downward and away from the unit to ensure good drainage.
24
50
5~10mm lower
Outdoor side
Figure 6
130
• Drill a hole at a slope so that the outside end is lower ( 5-10mm ) than the inside
end to ensure good drainage.
• Cut the Wall Sleeve to match the wall thickness and to pass the pipe through the
hole. ( Figure. 6 )
Figure 5