Operation; Starting The Unit - Cornelius Energize6 Service Manual

Backroom soda chiller package
Table of Contents

Advertisement

Energize6 Service Manual
S
U
TARTING THE
NIT
Publication Number: 621058457SER

OPERATION

The water bath must be filled up to the overflow with tap water. Refer to the Specifica-
tions on page 5 section of this manual for the amount of water required. To prevent
algae from forming in the water a mild disinfectant may be added to the solution.
To fill the unit, perform the procedure in Table 2.
Step
To fill the water bath loosen the screw on the left end of the unit and
1
remove the cover.
2
Lift the cover up, as shown in Figure 2 and store it in a safe place.
Open the fill valve, located near the right rear corner (near the tubing
3
entrance). See Figure 3 and Figure 4.
4
Fill the water bath to the top of the drain pipe, as shown in Figure 5.
Remove the front access panel (See Service Access on page 18) and
turn on the compressor by moving the compressor switch on the master
5
controller to the ON position, as shown in Figure 7. The compressor
should start and begin to cool after a 3 to 5 minute time delay.
6
The unit will start to build an ice bank. (approx. 2.5 hrs @ 75 °F)
Turn on the carbonator pump motors by moving the carbonator pump
switches to the ON position. (see Figure 7.)
If the water inlet pressure is within specifications, the carbonator pump
7
fills the carbonator and then switches off when the upper fill level is
reached. The carbonator tanks are located inside the water bath, as
shown in Figure 8 and Figure 9 on page 9.
Bleed air out of the carbonators and the dispensers by pulling up on the
8
ring attached to each relief valve, as shown in Figure 10.
Do not turn on the recirculation switches (Figure 7) until ice starts to form
9
on the evaporator coils.
10
Replace the cover on the unit.
- 6 -
Table 2.
Action
Figure 2.
© 2012, IMI Cornelius Inc.

Advertisement

Table of Contents
loading

Table of Contents