2 Delivery and handling
Transport
VPB/VPBS should be transported and stored vertically in
a dry place. The VPB/VPBS may, however, be carefully
laid on its back when being moved into a building.
Assembly
The water heater is only designed for upright installa-
tion.
Position the water heater on a firm base that can bear
its weight, preferably on a concrete floor or founda-
tion. Use the water heater's adjustable feet to obtain
a horizontal and stable set-up.
The area where VPB/VPBS is located must be equipped
with floor drainage.
Supplied components
VPB/VPBS Enamel
Potentiostat
Location
The kit of supplied items is placed on top of the product.
VPB/VPBS
Removing the covers
Front cover
0
R
1. Remove the screws from the lower edge of the front
cover.
2. Lift the cover out at the bottom edge and up.
Side covers
The side covers can be removed to facilitate the installa-
tion.
1. Remove the screws from the upper and lower edges.
2. Twist the cover slightly outward.
3. Move the cover backwards and slightly to the side.
4. Pull the cover to one side.
5. Pull the cover forwards.
2
1
Chapter 2 |
Delivery and handling
5