Replacing The Power Supply Board; Figure 3-21 Power Supply Board Replacement - Emerson Daniel 3818 Maintenance And Troubleshooting Manual

Lng liquid ultrasonic meter for cryogenic liquefied natural gas applications
Hide thumbs Also See for Daniel 3818:
Table of Contents

Advertisement

Maintenance and Troubleshooting Manual
3-9000-772 Rev B
3.4.6

Replacing the Power Supply Board

Procedure
1.
2.
3.
4.
5.

Figure 3-21 Power Supply Board replacement

A.
B.
C.
D.
A. Non-terminal end of Transmitter Electronics Enclosure
B. Power Supply board
C. I.S. Barrier board (inside the Guide Plate)
D. Backplane board
6.
7.
8.
9.
10.
11.
Replacing the Power Supply Board
If replacing the Power Supply board, disable electrical power to the meter.
Refer to
for the tools required to complete this procedure.
Table 3-4
Disconnect the Transmitter Electronics Enclosure security seals, loosen the end cap
security latches with a 3mm Allen wrench and remove both end caps.
Use a 1/8 inch (3 mm) flat head screw driver and remove the terminal blocks from the
Power Supply board, the CPU Module and the Optional I/O Module (Future).
for board locations and associated terminal blocks.
See Figure 3-17
Use a #1Standard Phillips head screw driver and remove the four Backplane board
screws from the enclosure standoffs.
Pull the Backplane board out of the enclosure. This disconnects the I.S. Barrier Board.
Lay the Backplane board down with the Acquisition Cable still attached (the Power
Supply board may remain attached to the Backplane when you remove it from the
enclosure).
Plug the new Power Supply board and the I.S. Barrier Board onto the Backplane Board.
Insert the Backplane, I.S. Barrier board and the Power Supply Board into the enclosure
and fully seat the CPU Module and Optional I/O Module (Future).
Attach the Backplane to the enclosure standoffs with the four Phillips head screws.
Use a 1/8 inch (3 mm) flat blade screw driver and install the terminal blocks on the CPU
Module, I.S. Barrier Board and the Power Supply.
Recheck the connections, wiring and switch settings before replacing the end caps.
Section 3: Meter maintenance
January 2018
65

Advertisement

Table of Contents
loading

Table of Contents