When to perform service procedures

Perform the following procedures as indicated:
Functional checkout on page 2-3: Used to verify normal operation. Must be performed
1.
before returning the ECG device to the user.
Electrical leakage current tests on page 2-6: Used to verify ECG device electrical safety.
2.
Must be performed after any internal repair (i.e., the case is opened), or to check for
possible damage (e.g., the ECG device is dropped).
Queue sensor calibration on page 2-8: Used to ensure paper feeds correctly. Must be
3.
performed if:
The paper tray assembly is removed or replaced
a.
The queue sensor board is replaced
b.
The power supply board is replaced
c.
The mainboard is replaced.
d.
70-00844-02 B