  • Page 1 Grid Installation Instructions Rev 0812...
  • Page 2 Grid Installation Instructions V5 – 8/23/12 Frames and Mini Frames FRAMES (and MEGA FRAMES) MINI FRAMES Cartons contain ONE of Three Types of Frames/ Mini Frames: a. End of Run (power/data opening in one end) b. Mid Frame (power/data openings in both ends) c.
  • Page 3 D. O-Legs - don’t attach to Grid Frames but rather attach to worksurfaces. In this application a Grid Frame straight or T-leg is NOT NEEDED in the end of Grid Frame runs. The Grid Frame is held up by a tether bracket that attaches the worksurface to the Frame (tether brackets are described later in this manual).
  • Page 4 2) When two or more frames are used in a row, legs are shared (as shown below). This will occur whenever the frame ends have cut-outs for electrical pass-thru. When only 2 frames form the Spine wall, only 1 End of Run frame should have the shared leg mounted prior flipping the frame over for final leg assembly.
  • Page 5 6) Top Caps must be removed by taking out the 4 - #8-32x3/4” Flat head screws(UZSCREWAL) on the top of each Grid Frame using a #15 Torque head drive. (Leave Top Caps off until step #24). 7) Attach in-line panel to panel connections using 10-24 screw (UZSCREWW) and 10-24 lock nut (UZWNUTB) through aligned holes at the top of the End Caps.
  • Page 6 Slide bracket so that you can attach screws into weld nuts in perpendicular Grid Frame. Once both screws have engaged and both frames are at right angles to each other, tighten all 4 screws.
  • Page 7 15. After the 3 Grid Frames are attached at the bottom, assemble the 120 triangle cover piece to the top of the end caps aligning the holes in the triangle cover with the holes in the end caps. Use 3 #10-24 x 3/ 8” (UZSCREWU) thread forming screws included in kit. 16.
  • Page 8 21. Pick the appropriate dataplate (provided) and add cabling and punch down (customer provided). 22. Enwork recommends that data cables be routed alongside power (power is shielded). If you want to use the chamber below you can feed the data cable through the bottom chamber.
  • Page 9 Note: When passing cables through leg with cut-out at the bottom, we recommend running a maximum of 12 data cables along with a Power infeed cable. Tiles 23. Once power and data are done you can slide the appropriate tiles into provided slots of the Grid Frames.
  • Page 10 4 - #8-32 screws (UZSCREWALZ without thread cutting). Worksurfaces and Supports 1. Mount legs to tops as specified in floor plan in preparation for attachment to Grid Frame. 2. If worksurfaces are ped supported then place peds into position per floor plan.
  • Page 11 4. Four - #10-24 x 3/8” Screws (UZSCREWW) and 4 - #10-24 Weld nuts (UZWNUTA) will be used for each Tether bracket. Install all screws in Tether brackets in approximate locations though do not tighten so that brackets can slide along grooves. Location of brackets will be determined by the following rules: 5.
  • Page 12 2. Tighten thread cutting screws (UZSCREWU) into inner holes, pushing spacer against acrylic topper screen. Trim Piece (UZBAND)  With every Frame you will receive a UZBAND trim tape. This tape is put on ONE side of the frame to cover up the holes (visual improvement). It is not a structural product. Peel the back side of the tape off and apply from one end to the other working the tape into the slot.
  • Page 13 Modesty Panel – Steel (optional add-on product) 1. Before attaching modesty panels, insert small bolts (#4-40x1/2” UZSCREWTS) through holes in top lip of modesty panel. Attach nuts (#4-40 UZWNUTC) to small bolts as shown below. 2. Slide modesty panel into bottom slot. The head of bolt holds modesty in slot. NOTE: the bolts/nuts will want to spin and have the nuts fall off.
  • Page 14 3. Once in place, tighten small nuts, return to step 6 of Assembly. Cable Trough and Brick Trough 1. Hang cable trough in top slot. Providing that the work surface tether bracket rules are followed, the cable troughs will be able to be placed into second slot up on bottom rail. 2.