Commissioning - Siemens SIRIUS 3RW55 Manual

Soft starters and solid-state switching devices
Hide thumbs Also See for SIRIUS 3RW55:
Table of Contents

Advertisement

Commissioning

6.1
Commissioning the 3RW55 soft starter
Procedure
1. Install the soft starter. (Page 41)
2. Connect up the soft starter. (Page 54)
3. Set the required language, the current date and time and the rated operational current.
Design and operator controls of the High Feature 3RW5 HMI (Page 151)
4. Parameterize the soft starter according to your application. (Page 69)
For support, use the application wizards and the automatic parameterization.
Application wizard (Page 76)
Automatic parameterization (Page 81)
5. Conduct a test run in order to test the application. (Page 162)
6. Optionally, you can conduct a diagnosis including self-test in order to test the correct
function of the devices. (Page 183)
7. Set the access protection (optional).
Defining the local access protection (PIN) (Page 167)
User login and logout (Page 169)
Sealing the soft starter (optional) (Page 77)
Result
The 3RW55 soft starter is ready for operation and protected against third-party access.
Alternatively commissioning can be performed via an optional communication module and
fieldbus system.
You will find additional information on operating modes and the respective control priority in
Chapter Operating modes and master control function (Page 14).
SIRIUS 3RW55 soft starter
Manual, 08/2018, A5E35630887002A/RS-AB/002
6
75