4.4.2 Routing and Placement

MSA recommends the use of at least two gas-monitoring points per chiller for sufficient detection
monitoring. Due to installation and application variations, each system must be analyzed individually.
Do a smoke test of the mechanical room to determine the flow pattern and allow for optimal placement
of the sample lines. Ventilation smoke tubes for this use are available from MSA (P/N 458480). For a
list of approved parts and how to order them, refer to Section 13, "Ordering Information".
Keep the total line length of a point, including the sample line and exhaust line, at less than 1200 ft
(366 m). Keep lines as short as possible to minimize the transport time of the device.
Transport Time
Line Length
4 pts
(ft)
0
19 s
50
19 s
100
19 s
150
19 s
200
19 s
250
19 s
300
1 m 35 s
350
1 m 35 s
400
2 m 51 s
450
2 m 51 s
500
2 m 51 s
*
Transport time is similar for all tubing configurations.
Typically, refrigerants collect near the floor. Install the sample points 12–18 in. (30–46 cm) above the
floor.
For installations where water condensation in the sample lines is likely, MSA recommends installing
a water trap filter such as a Parker P/N F504-01AHX67 or equivalent.
8 pts
16 pts
19 s
19 s
19 s
19 s
19 s
19 s
19 s
19 s
19 s
19 s
19 s
19 s
2 m 51 s
5 m 23 s
2 m 51 s
5 m 23 s
5 m 23 s
10 m 27 s
5 m 23 s
10 m 27 s
5 m 23 s
10 m 27 s
Chillgard 5000
Installation
US
19

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents