Service Interval Chart

CAUTION
If you leave the key in the ignition switch, someone could accidently start the engine and
seriously injure you or other bystanders.
Remove the key from the ignition switch before you perform any maintenance.
Pre-Maintenance
Procedures

Pre-Maintenance Safety

Before adjusting, cleaning, repairing, or leaving
the machine, do the following:
– Park the machine on a level surface.
– Move the throttle switch to the low-idle position.
– Disengage the cutting units.
– Lower the cutting units.
– Ensure that the traction is in neutral.
– Engage the parking brake.
– Shut off the engine and remove the key.
– Wait for all moving parts to stop.
– Allow machine components to cool before
performing maintenance.
If possible, do not perform maintenance while the
engine is running. Keep away from moving parts.
Use jack stands to support the machine or
components when required.
Carefully release pressure from components with
stored energy.
Figure 73

Lubrication

Greasing the Bearings and
Bushings
Service Interval: Every 50 hours (and immediately
Lubricate all grease fittings for the bearings and
bushings with No. 2 lithium grease.
The grease fitting locations and quantities are as
follows:
Pump driveshaft (3)
49
after every washing).
(Figure
74)
Figure 74
decal125-2927
g021216

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

03607Reelmaster 5410-d03606

Table of Contents