TrueBlend™
1. Change the WCN values for all loaders
in blender 1 and 2 to 240. The loaders
will then use the waiting list and the
blower connected to blender 2. In this
case the operator will need to change
the fields for all loaders used on the
system. This is similar to example 1.
2. Change the WCN value for the blower in
blender 1 to reference the blower in
blender 2. In this case only one item, the
blower WCN, needs to be changed.
When this change is made, the waiting list is still contained in blender 1, but once
a loader requests operation, a message is sent to the pump logic in blender 2.
The complete setup looks like this:
Edition: February 2007
Operation
107