All packing materials and restraints have been removed from each cabinet.
-
Each cabinet in the UPS system is placed in its installed location.
-
All cabinets are bolted together.
-
A ground bond is installed between all cabinets that are bolted together.
-
All switchboards, conduits, and cables are properly routed to the UPS.
-
Power cables are terminated on AC Input terminals (UPS Cabinet) (E1---E3).
-
Power cables are terminated on Bypass Transformer input terminals (UPS Cabinet)
-
(E13---E15).
Power cables are terminated on AC Output terminals (UPS Cabinet) (E9---E12).
-
Power cables are terminated on DC Input terminals (UPS Cabinet) (E4---E5).
-
Power cables are terminated on bypass terminals (E19---E21).
-
Power cables are terminated on the CB1 input breaker (E33---E35 ).
-
Power cables are terminated on output terminals (E25---E27).
-
A ground conductor is properly installed.
-
If N is used, no other N---G bonds exist downstream from the UPS.
-
Battery cables and harness are terminated on the CB2 battery breaker E31 and E32.
-
The area around the installed UPS system is clean and dust-free. (It is recommended
-
that the UPS be installed on a sealed concrete pad on a sealed concrete floor.)
Adequate workspace exists around the UPS and other cabinets.
-
Adequate lighting is provided around all UPS equipment.
-
A 120V service outlet is located within 25 feet of the UPS equipment.
-
Powerware BPIII Harsh Environment UPS 50--75 kVA Installation and Operatio
164201261 Rev. F 111503
n
19

Advertisement

Table of Contents
loading

This manual is also suitable for:

Bpiii

Table of Contents