Vespa GTS Super 300 ie (2008)
Injection
Check the power supply line of the injection load
solenoid energising coil: after switching to "ON",
make sure there is battery voltage, for two sec-
onds, between the Red-White cable and Black-
Purple cable of the solenoid control base. If there
is not, check the continuity of the Red-White cable
between the fuse box under the saddle hinge and
the remote control base and of the Black-Purple
cable between pin 22 of the control unit and the
remote control base.
N.B.
CONTINUITY TESTS MUST BE CARRIED OUT WITH THE
COMPONENTS DISCONNECTED. (RELAYS, CONTROL
UNIT, FUSES ETC.).