See Graphic: wc_gr002435
8.10.10 Grease the adjusting point circle (a) of the main cradle and the bottom
8.10.11 Using an appropriate crane or hoist, lift the main mast onto the top of
8.10.12 Secure the main mast to the main cradle with the washer and nut (c).
8.10.13 Position the cable clip (d), on the tower supply cable, just below the
8.10.14 Thread the tower supply cable through the eyes (e) on the main mast.
8.10.15 Thread the tower supply cable through the clamp (f) at the front of the
8.10.16 Feed the tower supply cable into the control box and connect the wires
8.10.17 Secure the tower supply cable in the cable clip (l) and secure the cable
wc_tx000428gb.fm
Reassembly:
pivot point (b) of the main mast.
the generator enclosure. Slide the bottom of the main mast into the
main cradle.
lower curled portion of the cable. Then, secure the cable clip to the end
of the main mast.
machine; leave a loop (g) of cable large enough so there is enough
slack in the cable to raise the mast.
to the appropriate locations (h & i). Refer to the wiring diagram.
Tighten the cable clamp (j), organize the wires with new wire ties (k),
and re-install the control panel cover.
clip to the underside of the top enclosure panel.