Installing a Replacement Microinverter

1. With the silver side of the microinverter facing up and the black side facing down, attach the
replacement microinverter to the PV racking using hardware recommended by your PV racking
vendor.
2. If you are using grounding washers (e.g., WEEB) to ground the chassis of the microinverter, the
old grounding washer should be discarded, and a new grounding washer must be used when
installing the replacement microinverter. Torque the microinverter fasteners to the values shown:
NOTE: Using a power screwdriver to tighten the grounding clamp screw is not
recommended due to the risk of thread galling.
3. If you are using a grounding electrode conductor to ground the microinverter chassis, attach the
grounding electrode conductor to the microinverter ground clamp.
4. Connect the microinverter. There are two latching mechanisms within the connectors. Listen for
two clicks as the connectors engage. Ensure that both latching mechanisms have engaged.
5. Mount the PV module above the microinverter.
6. First connect the positive DC wire from the PV module to the negatively marked DC connector
(male pin) of the microinverter. Then connect the negative DC wire from the PV module to the
positively marked DC connector (female socket) of the microinverter.
7. Energize the AC branch circuit breaker, and verify operation of the replacement microinverter by
checking the indicator light on the underside of the microinverter. You may need a handheld
mirror to see the indicator light.
8. Initiate a device scan at the Envoy. To do this, press and hold the Menu button on the Envoy for
two seconds to bring up the Envoy menu on the LCD window. When the LCD window displays
"Enable Communication Check", release the Menu button.
9. Use Enlighten's Array Builder function to add the newly detected microinverter to the virtual
array.
24
6 mm (1/4") mounting hardware – 5 N m (45 in-lbs) minimum
8 mm (5/16") mounting hardware – 9 N m (80 in-lbs) minimum