7.1

Overview

Prerequisites
1. The device has been installed.
2. The device has been connected in accordance with the possible connection methods.
The device must be connected to the bus for communication via the RS 485 interface.
Steps for starting up the device
1. Apply the supply voltage
2. Parameterize the device
3. Apply the measuring voltage
4. Apply the measuring current
5. Check the displayed measured values
NOTICE
Check the connections
Incorrect connection can result in malfunctions and failure of the device.
Before starting up the SENTRON PAC3100, check that all connections are correct.
7.2

Applying the supply voltage

A supply voltage is required to operate the device. Please consult the technical data or the
type plate for the type and level of the possible supply voltage.
Do not apply voltage in excess of the rated voltage limit
Failure to do so may result in death, serious injury, or property damage
The limits given in the technical data and on the type plate must not be exceeded even at
startup or when testing the device.